Serial No. |
Description of Work |
Service Order/ LOA/ Reference No |
Client / Main Client |
Work Order Value |
Remarks |
1 |
Bitumen Painting in NDCT (Natural Draft Cooling Tower) - 2 |
330009765 Dated 22.03.2013 |
BGR Energy Systems Limited. |
8,368,234.00 |
Completed. |
Rayalaseema Thermal Power Station,Kadapa, Andhra Pradesh. |
2 |
Beam Grouting ln NDCT (Natural Draft Cooling Tower) - 1 & 2 |
330009845 Dated 03.08.2013 |
BGR Energy Systems Limited |
4,710,936.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
3 |
Assembly & Erection of Fills & Drift |
3300010403 dated 03.12.2013 |
BGR Energy Systems Limited |
5,332,605.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
4 |
Construction Of Peripheral Beam&Beam Below Hwd |
3300007574 Dated 08.06.2012 |
BGR Energy Systems Limited |
2,924,789.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
5 |
Febrication & Erection Of Cage Ladder & Handrail |
3300007575 Dated 08.06.2012 |
BGR Energy Systems Limited |
4,400,931.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
6 |
Platform & Corbel Work NDCT |
3300007575 Dated 08.06.2012 |
BGR Energy Systems Limited |
11,623,618.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
7 |
Cement Painting Ln- NDCT 1 & 2 |
3300006783 Dated 08.06.2012 |
BGR Energy Systems Limited |
4,314,624.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
8 |
Construction Of Shell & Int Fill Str NDCT-2 |
3300006615 Dated 08.06.2012 |
BGR Energy Systems Limited |
128,258,988.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
9 |
Construction of Int Fill Structure NDCT-1 |
3300005499 Dated 08.06.2012 |
BGR Energy Systems Limited |
30,467,205.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
10 |
Construction Of Shell NDCT-1 |
3300005501 Dated 08.06.2012 |
BGR Energy Systems Limited |
24,973,469.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
11 |
Ass & Er of Fills & Drift Ellm Unit -1 |
3300008554 Dated 20.11.2012 |
BGR Energy Systems Limited |
5,348,336.00 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
12 |
Bitumen Painting In- NDCT |
3300007290 Dated 03.04.2013 |
BGR Energy Systems Limited |
8,311,564.80 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
13 |
Appl of Refactory Katpp-11 |
3300007161 Dated 26.10.2012 |
BGR Energy Systems Limited |
2,715,067.04 |
Completed. |
Kalisindh Thermal Power Station,Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUNL) Jhalawar (Rajasthan) |
14 |
Construction of Chlmney Shell Auxiliary Cooling Tower (IDCT) |
LOI Dated 12.11.2013 |
BGR Energy Systems Limited |
30,892,570.00 |
Completed. |
|
|
Total Amount |
272,642,936.84 |
|